[Utility Outage] Completed HVAC Outage - 07/29/2014 09:00

Carroll W. Jones jonesc at jlab.org
Wed Jul 30 20:46:06 EDT 2014


The following HVAC Outage has been Completed:

Outage:      CUP Chiller Factory Field Engineer Performance Evaluation
Proposed By: Carroll W. Jones
Start Time:  07/29/2014 09:00
End Time:    07/30/2014 17:00

Description/Impacts:
Chiller factory engineer will not arrive on site until late Tuesday afternoon when he will get badged and complete required training.  Evaluation of the chiller system will begin Wednesday morning.  The full load test will not occur until sometime Wednesday afternoon.

For additional information or clarification, please contact Carroll Jones at 757-876-1778.

_________________________________________________________________________________
CUP Chiller performance is being evaluated by the factory field engineer to verify the chiller can produce 800 tons.  At some point, 800 tons of cooling load must be moved to the CUP Chiller.  The cooling load currently being cooled by the Test Lab basement chillers (EEL Building, Test Lab North Addition, and Accelerator Chilled Water Loop) will be moved to the CUP Chiller in addition to the CEBAF Center F-Wing, the TLA, and the Test Lab Highbay.  The Test Lab Cooling Tower condenser water supply temperature must also be raised up to 85 degrees F.  During the actual full load test, the actual cooling load will be more than 800 tons so the chilled water supply temperature will rise above the normal 42 to 44 degrees F.  Depending upon how  long the full load test lasts, the temperature in some areas may drift up .  Major impact to specific areas is not anticipated, but all areas will be monitored and steps taken (transfer part of the load back to the Test Lab basement chillers)
  to minimize impacts to site operations.  Areas more sensitive to chilled water supply temperature change such as the F-Wing Data Center will be notified when the full load test is to begin and when the chilled water plant is returned to normal operation.

For additional information or clarification, please contact Carroll W. Jones at 757-876-1778.

Impacted Areas:
	Bldg 01: North LINAC
	Bldg 02: South LINAC
	Bldg 21: North Extractor Service
	Bldg 38: South Access
	Bldg 39: East Arc Service
	Bldg 40: West Arc Service
	Bldg 45: West Arc Service
	Bldg 49: East Arc Service
	Bldg 50: East Arc Service
	Bldg 53: Injector Service
	Bldg 56: West Arc Service
	Bldg 63: East Arc Service
	Bldg 67: North Access
	Bldg 68: West Arc Service
	Bldg 82: South Extractor Service
	Bldg 58: Test Lab
	Bldg 90: Experimental Equipment Lab

For more details, visit the webpage listed below:
https://cc.jlab.org/cgi-bin/infrastructure/Outage/OutageView?ident=4