The following Power Outage has been Proposed:
Outage: LINAC Power Outages - Various Panels
Proposed By: Paul Powers
Start Time: 06/10/2014 06:00
End Time: 06/12/2014 10:00
Description/Impacts:
Panels, NL-L1, NL-PP1, NL-P3, NL-L3, SL-L3, SL-PP8, SL-L1, SL-PP1. Work will be done in sequence so that once one panel is complete, the second will start and so forth to minimize the impact of interruptions. Therefore, there will be staggered outages. Work will start in the North LINAC first, then progress to the South LINAC. Any questions, call Jason Willoughby. Work will start at 6 AM each day and will be concluded by 10 AM each day.
Impacted Areas:
Bldg 01: North LINAC
Bldg 02: South LINAC