[Utility Outage] Proposed Power Outage - 06/23/2014 07:00
Michele Solaroli
solaroli at jlab.org
Wed Jun 18 11:23:55 EDT 2014
The following Power Outage has been Proposed:
Outage: UIM Electrical Distribution Upgrade - CHL Loop
Proposed By: Michele Solaroli
Start Time: 06/23/2014 07:00
End Time: 07/03/2014 14:00
Description/Impacts:
CHL1 to CHL1 Comp MDP will be down for electrical upgrade of secondary cables 6/23 - 6/25
CHL2 to CHL1 Comp MDP will be down for electrical upgrade of secondary cables 6/26 - 7/1
Testing and Final Terminations 7/2 - 7/3
Impacted Areas:
Bldg 08: Central Helium Liquefier
For more details, visit the webpage listed below: