The following Power Outage has been Proposed:
Outage: UIM Electrical Distribution - SOUTH LOOP
Proposed By: Michele Solaroli
Start Time: 06/23/2014 07:00
End Time: 06/26/2014 14:00
Description/Impacts:
Replace primary cables MVSW#7 to MVSW#3 6/23 - 6/24
Replace primary cables MVSW#3 to Unitsub FEL 6/25 - 6/25
Testing & Final Terminations 6/26 - 6/26
Impacted Areas:
Bldg 18: Free Electron Laser
Bldg 36: General Purpose Building