[Utility Outage] Scheduled Power Outage - 06/23/2014 07:00

Michele Solaroli solaroli at jlab.org
Thu Jun 19 10:55:00 EDT 2014


The following Power Outage has been Confirmed:

Outage:      UIM Electrical Distribution Upgrade - NORTH LOOP
Proposed By: Michele Solaroli
Start Time:  06/23/2014 07:00
End Time:    06/30/2014 17:00

Description/Impacts:
Verification of Primary Cabling - Unitsub #5 to MH5 6/23 - 6/23  Power will be interrupted at Central Chiller and Data Center Alt Feed. Two of the three basement chillers will be off.  Temperatures may rise in building 90, 58 North Addition, UHV furnace, and accelerator service building cooled by accelerator chilled water loop.  

Replacement of primary cables MH5 to MVSW#2  6/14 - 6/25 

Replacement of primary cables MVSW#2 to Unitsub W5 6/26 - 6/26  
Testing & Final Termination 6/30 - 6/30

For all outage impacts, contact Dianne Owens, Steve Suhring or Walt Akers.  Panel board schedules for each building are located in M:\UIM_Interface_Coordination\Electrical Distribution\panel board schedules_2014 as of 12 May 2014

Impacted Areas:
	Bldg 01: North LINAC
	Bldg 02: South LINAC
	Bldg 21: North Extractor Service
	Bldg 38: South Access
	Bldg 39: East Arc Service
	Bldg 40: West Arc Service
	Bldg 45: West Arc Service
	Bldg 49: East Arc Service
	Bldg 50: East Arc Service
	Bldg 53: Injector Service
	Bldg 56: West Arc Service
	Bldg 67: North Access
	Bldg 68: West Arc Service
	Bldg 82: South Extractor Service
	Bldg 58: Test Lab
	Bldg 90: Experimental Equipment Lab

For more details, visit the webpage listed below:
https://cc.jlab.org/cgi-bin/infrastructure/Outage/OutageView?ident=10