[Utility Outage] Scheduled Power Outage - 06/23/2014 07:00
Michele Solaroli
solaroli at jlab.org
Thu Jun 19 10:55:24 EDT 2014
The following Power Outage has been Confirmed:
Outage: UIM Electrical Distribution Upgrade - CHL Loop
Proposed By: Michele Solaroli
Start Time: 06/23/2014 07:00
End Time: 07/03/2014 14:00
Description/Impacts:
CHL1 to CHL1 Comp MDP will be down for electrical upgrade of secondary cables 6/23 - 6/25
CHL2 to CHL1 Comp MDP will be down for electrical upgrade of secondary cables 6/26 - 7/1
Testing and Final Terminations 7/2 - 7/3
For all outage impacts, contact Dianne Owens, Steve Suhring or Walt Akers. Panel board schedules for each building are located in M:\UIM_Interface_Coordination\Electrical Distribution\panel board schedules_2014 as of 12 May 2014
Impacted Areas:
Bldg 08: Central Helium Liquefier
For more details, visit the webpage listed below:
https://cc.jlab.org/cgi-bin/infrastructure/Outage/OutageView?ident=7