[Utility Outage] Scheduled Power Outage - 05/09/2014 07:00

Paul Powers powersp at jlab.org
Tue May 6 14:53:19 EDT 2014


The following Power Outage has been Confirmed:

Outage:      Counting House and Bldg 98 Emergency Power Outage
Proposed By: Paul Powers
Start Time:  05/09/2014 07:00
End Time:    05/09/2014 17:00

Description/Impacts:
This power outage will be for 8+ hours.    All power to panels CHEM, B4EM (Bldg 98) and CHEMP2 will be secured for 8 hours to finish the construction.  

Impacted Areas:
	Bldg 97: Counting House
	Bldg 98: Physics Fabrication Building

For more details, visit the webpage listed below:
https://cc.jlab.org/cgi-bin/infrastructure/Outage/OutageView?ident=7



More information about the Fac_outages mailing list