The following Road Closure has been Confirmed:

Outage:      Sills at Entrances to Truck Ramps for Hall A & B
Proposed By: Suresh Chandra
Start Time:  08/17/2015 08:00
End Time:    10/01/2015 17:00

Description/Impacts:
Sill at Hall B has been installed.  Concrete on both sides of the sill needs to be dressed in certain length of sill to avoid trip hazard.  This work is planed to be done on 8/28/2015.

Work for Sill at Hall A is complete and traffic can resume.
Work on Hall B Sill will start on 8/24/2015 (Monday) and the traffic there will be blocked.

Sill at Hall A has been installed.  The entrance will be ready for use starting tomorrow (8/21/2015)
Work for Sill at Hall B will also start tomorrow (8/21/2015).


Steel Sills are to be installed at Entrances to Truck Ramps for Halls A & B.  During this period vehicular traffic thru the ramps for Hall A & B will be interrupted.  Job will first start at Hall A & then at Hall B.  If you have any questions, please contact me.
Suresh
Tel. 7248


Impacted Areas:
	Bldg 94: Experimental Hall B
	Bldg 101: Experimental Hall A

For more details, visit the webpage listed below:
https://cc.jlab.org/cgi-bin/infrastructure/Outage/OutageView?ident=50