The following General Outage has been Completed:
Outage:      CEBAF Sidewalk Closure
Proposed By: Russell Mattox
Start Time:  11/23/2015 07:00
End Time:    12/04/2015 17:00
Description/Impacts:
Continue the replacement of the chill water lines from TEDF to CEBAF Data Center
Excavating across the sidewalk from CEBAF main parking lot to  the B Wing entrance door of CEBAF Center
Impacted Areas:
	Bldg 12: CEBAF Center
For more details, visit the webpage listed below:
https://cc.jlab.org/cgi-bin/infrastructure/Outage/OutageView?ident=74
    
    