The following Power Outage has been Completed:
Outage:      UIM Electrical Upgrade - End Station Unitsub T2
Proposed By: Michele Solaroli
Start Time:  12/22/2014 08:00
End Time:    12/31/2014 12:00
Description/Impacts:
Unitsub T2 secondaries will be replaced.  Outage will impact all clean power in Hall A, Hall B and Hall C. 
If you have any questions, please contact Walt Akers, Paul Powers or Michele Solaroli
Impacted Areas:
	Bldg 94: Experimental Hall B
	Bldg 96: Experimental Hall C
	Bldg 101: Experimental Hall A
For more details, visit the webpage listed below:
https://cc.jlab.org/cgi-bin/infrastructure/Outage/OutageView?ident=3
    
    