The following Power Outage has been Confirmed:
Outage: Test Lab Switchboard 2
Proposed By: J. Willoughby
Start Time: 07/21/2015 06:00
End Time: 07/21/2015 07:00
Description/Impacts:
Remove power from Switchboard 2 to take measurements for CTs. Impacts the following:
Highbay 480V and 208V power
The Crane
Both rollup doors
CMTF Doors
Highbay networking
Office area (sec G) power and lighting
Elevator
All of the North Addition (including HDIce, but they have a generator)
Impacted Areas:
Bldg 58: Test Lab