The following Power Outage has been Completed:
Outage: Energize test lab High bay receptacles
Proposed By: Josh Caterbone
Start Time: 07/15/2015 06:00
End Time: 07/15/2015 07:00
Description/Impacts:
This outage is to hook up circuits to newly installed receptacles in High Bay area of the test Lab. Panel FEL-P1 will be affected. This is a 120/208 volt panel. This panel controls Receptacles in the test cave, lights in the test cave, receptacles on the outside wall of the laser room, air handler, heat pump, disconnect-foil skids. This will be a 30-45 minute power outage.
Impacted Areas:
Bldg 58: Test Lab