[Utility Outage] Scheduled Power Outage - 08/03/2016 09:00
Michele Solaroli
solaroli at jlab.org
Mon Aug 1 13:35:22 EDT 2016
The following Power Outage has been Confirmed:
Outage: UIM CTF Bldg - ATS Start-up Check
Proposed By: Michele Solaroli
Start Time: 08/03/2016 09:00
End Time: 08/03/2016 09:30
Description/Impacts:
Contractor will be performing start-up check on the ATS. Will require brief outage to ensure emergency systems still engages when required. Will only effect CRYO-EM-1 and the circuits fed from it.
The following items are scheduled under CRYO-EM-1
control room receptacles
FACU
exhaust fan EF-2
exhaust fan EF-5
security panel
control room lights
control room heat pump/mini splits
Impacted Areas:
Bldg 57: Cryogenic Test Facility
For more details, visit the webpage listed below:
https://cc.jlab.org/cgi-bin/infrastructure/Outage/OutageView?ident=1
More information about the Fac_outages
mailing list