The following Power Outage has been Proposed:
Outage:      Test Lab DP-Lab-9
Proposed By: j. willoughby
Start Time:  08/09/2016 07:00
End Time:    08/09/2016 12:00
Description/Impacts:
Remove power from DP-LAB-9 and AP-LAB-15 to tie in rack power in high bay.  This will remove all 480V, 208/120V power from the ITF Control Room, ITF cave 1 and 2 area, and all power in the racks above the ITF Cave 1 area.
Impacted Areas:
	Bldg 58: Test Lab
For more details, visit the webpage listed below:
https://cc.jlab.org/cgi-bin/infrastructure/Outage/OutageView?ident=2
    
    
More information about the Fac_outages