[Utility Outage] Completed Power Outage - 12/06/2016 09:00
J. Willoughby
jasonw at jlab.org
Thu Dec 8 06:14:57 EST 2016
The following Power Outage has been Completed:
Outage: Data Center Wall Outlets
Proposed By: J. Willoughby
Start Time: 12/06/2016 09:00
End Time: 12/06/2016 10:00
Description/Impacts:
Remove power from panel RP1F. This will remove power from all the wall outlets in F112.
Impacted Areas:
Bldg 12: CEBAF Center
For more details, visit the webpage listed below:
https://cc.jlab.org/cgi-bin/infrastructure/Outage/OutageView?ident=2