[Utility Outage] Completed Power Outage - 01/28/2016 08:00

j. willoughby jasonw at jlab.org
Fri Feb 26 07:03:55 EST 2016


The following Power Outage has been Completed:

Outage:      Test Lab - North Addition
Proposed By: j. willoughby
Start Time:  01/28/2016 08:00
End Time:    01/28/2016 09:00

Description/Impacts:
Remove power from P3H4 in the Test Lab North Addition.  This will impact all the 480/277 power on the second floor of the north annex. This will impact a few Air Handlers in the North Addition as well

Impacted Areas:
	Bldg 58: Test Lab

For more details, visit the webpage listed below:
https://cc.jlab.org/cgi-bin/infrastructure/Outage/OutageView?ident=82