The following Power Outage has been Confirmed:

Outage:      Test Lab Office Area
Proposed By: J. Willoughby
Start Time:  01/15/2016 06:30
End Time:    01/15/2016 08:00

Description/Impacts:
Remove power from AP-1G-1 to tie in power for receptacles.  This will remove all 208/120 power from the first floor Test Lab Office Area.

Impacted Areas:
	Bldg 58: Test Lab