[Utility Outage] Scheduled Power Outage - 01/15/2016 08:00
J. Willoughby
jasonw at jlab.org
Thu Jan 14 09:23:59 EST 2016
The following Power Outage has been Confirmed:
Outage: Test Lab EAP-1200
Proposed By: J. Willoughby
Start Time: 01/15/2016 08:00
End Time: 01/15/2016 09:00
Description/Impacts:
Remove power from EAP-1200 to tie in power for UITF panel. This will remove 208/120 emergency power from the PSS rack in the CMTF Control Room, the network rack in the CMTF control room, and the Data racks servicing the east side of the Test Lab highbay.
Impacted Areas:
Bldg 58: Test Lab
For more details, visit the webpage listed below:
https://cc.jlab.org/cgi-bin/infrastructure/Outage/OutageView?ident=85
More information about the Fac_outages
mailing list