The following General Outage has been Confirmed:

Outage:      B97, HallA, HallB, and HallC Access Control power supply replacement
Proposed By: John Riesbeck
Start Time:  07/12/2016 13:39
End Time:    07/12/2016 13:39

Description/Impacts:
This will make the B97 Counting House main door electronic lock not function and Hall B will be unlocked.  This will be for most of the day.  Hall A and C are already unlocked so they should not see any changes in the function of the system.

Impacted Areas:
	Bldg 94: Experimental Hall B
	Bldg 96: Experimental Hall C
	Bldg 97: Counting House
	Bldg 101: Experimental Hall A

For more details, visit the webpage listed below:
https://cc.jlab.org/cgi-bin/infrastructure/Outage/OutageView?ident=128