[Utility Outage] Proposed Power Outage - 07/25/2016 08:00
Bob Bennett
bennettr at jlab.org
Thu Jul 21 09:31:00 EDT 2016
On 7/21/2016 7:46 AM, J. Willoughby wrote:
> The following Power Outage has been Proposed:
>
> Outage: Test Lab MCC-1B
> Proposed By: J. Willoughby
> Start Time: 07/25/2016 08:00
> End Time: 07/25/2016 09:00
>
> Description/Impacts:
> Remove power from MCC-1B to tie in new circuits into bucket 5/1 and 5/2. This will remove power from the following:
>
>
> CMTF Test Cave 120/208 Power
> LCW Pump
> 58-PCP-a
> 58-PCP-2
> 58-ACP-1
> 58-ACP-2
> 58-CWP-1
> PCH-1
> GSP-1
> Air Compressor 2
>
>
> Impacted Areas:
> Bldg 58: Test Lab
>
> For more details, visit the webpage listed below:
> https://cc.jlab.org/cgi-bin/infrastructure/Outage/OutageView?ident=130
>
> _______________________________________________
> Fac_outages mailing list
> Fac_outages at jlab.org
> https://mailman.jlab.org/mailman/listinfo/fac_outages
Jason,
I addressed this at the meeting this morning. The consensus is it cannot
happen until the cryomodule in the
Test Cave is moved out. Cooling down is going on now. The tentative date
to move the module out of the test cave
is Aug. 10th. This would be the earliest your outage could be done.