[Utility Outage] Proposed Power Outage - 07/25/2016 08:00

Bob Bennett bennettr at jlab.org
Thu Jul 21 09:33:49 EDT 2016


On 7/21/2016 9:31 AM, Bob Bennett wrote:
> On 7/21/2016 7:46 AM, J. Willoughby wrote:
>> The following Power Outage has been Proposed:
>>
>> Outage:      Test Lab MCC-1B
>> Proposed By: J. Willoughby
>> Start Time:  07/25/2016 08:00
>> End Time:    07/25/2016 09:00
>>
>> Description/Impacts:
>> Remove power from MCC-1B to tie in new circuits into bucket 5/1 and 
>> 5/2.  This will remove power from the following:
>>
>>
>> CMTF Test Cave 120/208 Power
>> LCW Pump
>> 58-PCP-a
>> 58-PCP-2
>> 58-ACP-1
>> 58-ACP-2
>> 58-CWP-1
>> PCH-1
>> GSP-1
>> Air Compressor 2
>>
>>
>> Impacted Areas:
>>     Bldg 58: Test Lab
>>
>> For more details, visit the webpage listed below:
>> https://cc.jlab.org/cgi-bin/infrastructure/Outage/OutageView?ident=130
>>
>> _______________________________________________
>> Fac_outages mailing list
>> Fac_outages at jlab.org
>> https://mailman.jlab.org/mailman/listinfo/fac_outages
> Jason,
> I addressed this at the meeting this morning. The consensus is it 
> cannot happen until the cryomodule in the
> Test Cave is moved out. Cooling down is going on now. The tentative 
> date to move the module out of the test cave
> is Aug. 10th. This would be the earliest your outage could be done.
> Bob
>
> _______________________________________________
> Fac_outages mailing list
> Fac_outages at jlab.org
> https://mailman.jlab.org/mailman/listinfo/fac_outages





More information about the Fac_outages mailing list