The following Power Outage has been Completed:

Outage:      CEBAF Center F-Wing Data Center
Proposed By: Paul Powers
Start Time:  09/09/2016 08:00
End Time:    09/09/2016 09:00

Description/Impacts:
Power outage to panel MDBBA to install neutrals for two new panelboards.  Outage has already been coordinated with Sandy Philpott.  Affects all cooling for Data Center.

Impacted Areas:
	Bldg 12: CEBAF Center