[Utility Outage] Scheduled Power Outage - 08/22/2017 06:00
    Paul Powers 
    powersp at jlab.org
       
    Mon Aug 21 10:41:57 EDT 2017
    
    
  
The following Power Outage has been Confirmed:
Outage:      Power Outage - SSC Bldg 28 panel P12 in Procurement Conference Room
Proposed By: Paul Powers
Start Time:  08/22/2017 06:00
End Time:    08/24/2017 07:00
Description/Impacts:
Power outage in this panel to install circuits for Groundbreaking Ceremony.  Power Outage will start at 6 AM each morning and finish by 8 AM each morning.
Impacted Areas:
	Bldg 28: SSC (VARC)
For more details, visit the webpage listed below:
https://cc.jlab.org/cgi-bin/infrastructure/Outage/OutageView?ident=5
    
    
More information about the Fac_outages
mailing list