[Utility Outage] Proposed Power Outage - 12/20/2018 08:00
J. Willoughby
jasonw at jlab.org
Tue Dec 18 09:07:25 EST 2018
The following Power Outage has been Proposed:
Outage: Test Lab Addition Mezzanine
Proposed By: J. Willoughby
Start Time: 12/20/2018 08:00
End Time: 12/20/2018 09:00
Description/Impacts:
Remove power from panel AP-HVAC-M-1 for repairs. This removes power from the mezzanine AHU lights and receptacles, water heater, and general receptacles up on the TLA mezzanine.
Impacted Areas:
Bldg 58: Test Lab
For more details, visit the webpage listed below:
https://cc.jlab.org/cgi-bin/infrastructure/Outage/OutageView?ident=1
More information about the Fac_outages
mailing list