The following Power Outage has been Proposed:
Outage:      Bldg 87: Accelerator Maintenance & Support Power outage
Proposed By: John Riesbeck
Start Time:  08/14/2019 07:00
End Time:    08/14/2019 08:00
Description/Impacts:
Shut down the 120/208v electrical panel P3;
RM 106 REC.			
RM 106 REC. TEST RACK 1			
RM 106 REC. TEST RACK 2			
RM 106 TEST RACK 1-1 / 1-2 / 2-1			
			
			
RM 106 TEST RACK 2-2			
MEN'S RR GFCI REC. RM 103			
WATER COOLER			
WOMENS'S RR			
AHU-8 CONDENSATE PUMP			
RM 106 REC.			
HALLWAY REC.			
HALLWAY REC.			
RM 108 REC.			
RM 107 REC.			
RM 104 REC.			
RM 105 REC.			
HALLWAY REC.		
SOUTH OUTSIDE GFCI			
Impacted Areas:
	Bldg 87: Accelerator Maintenance & Support