The following Power Outage has been Completed:
Outage: Bldg 87: Accelerator Maintenance & Support Power outage
Proposed By: John Riesbeck
Start Time: 08/14/2019 07:00
End Time: 08/14/2019 08:00
Description/Impacts:
Shut down the 120/208v electrical panel P3-
RM 106 REC.
RM 106 REC. TEST RACK 1
RM 106 REC. TEST RACK 2
RM 106 TEST RACK 1-1 / 1-2 / 2-1
RM 106 TEST RACK 2-2
MEN'S RR GFCI REC. RM 103
WATER COOLER
WOMENS'S RR
AHU-8 CONDENSATE PUMP
RM 106 REC.
HALLWAY REC.
HALLWAY REC.
RM 108 REC.
RM 107 REC.
RM 104 REC.
RM 105 REC.
HALLWAY REC.
SOUTH OUTSIDE GFCI
Impacted Areas:
Bldg 87: Accelerator Maintenance & Support