The following Power Outage has been Proposed:

Outage:      Bldg 58 panels DP-LAB-10 and AP-LAB-16 power outage
Proposed By: John Riesbeck
Start Time:  09/05/2019 07:00
End Time:    09/05/2019 09:00

Description/Impacts:
Remove power to electrical panel DP-LAB-10 to change out a breaker  to support HDIce testing.

Includes:
Lights in the test cave 
120/208 panel AP-LAB-16;
FEED TO ITF-P3
4 circuits of 3P REC. L21-30R	
and 3 receptacle circuits		
			
			

			


Impacted Areas:
	Bldg 58: Test Lab

For more details, visit the webpage listed below:
https://cc.jlab.org/cgi-bin/infrastructure/Outage/OutageView?ident=3