[Utility Outage] Completed Power Outage - 11/17/2020 07:30

todd kujawa kujawa at jlab.org
Tue Nov 17 09:46:39 EST 2020


The following Power Outage has been Completed:

Outage:      Panel maintenance
Proposed By: todd kujawa
Start Time:  11/17/2020 07:30
End Time:    11/17/2020 11:00

Description/Impacts:
Buildings 49, 39, 23, 63, and 64 will be without power while circuit breakers and electrical switches are cycled. Work is expected to last no more than 2 hours.

Impacted Areas:
	Bldg 23: Experimental Staging Building
	Bldg 39: East Arc Service
	Bldg 49: East Arc Service
	Bldg 63: East Arc Service

For more details, visit the webpage listed below:
https://cc.jlab.org/cgi-bin/infrastructure/Outage/OutageView?ident=4