[Utility Outage] Completed Power Outage - 11/18/2020 07:15
    powers 
    powersp at jlab.org
       
    Wed Nov 18 08:20:16 EST 2020
    
    
  
The following Power Outage has been Completed:
Outage:      Power Outage - Bldg 52, 54, 34
Proposed By: powers
Start Time:  11/18/2020 07:15
End Time:    11/18/2020 07:45
Description/Impacts:
A brief outage to reconfigure the power supply to the Campus from the Accelerator Feeder back to the normal 22 MVA Feeder.  Outage complete - no issues.
Impacted Areas:
	Bldg 52: EHS&Q Building
	Bldg 54: Radcon Calibration
	CMSA Laydown Area
For more details, visit the webpage listed below:
https://cc.jlab.org/cgi-bin/infrastructure/Outage/OutageView?ident=2
    
    