[Utility Outage] Scheduled Power Outage - 05/07/2021 07:00
kujawa
kujawa at jlab.org
Thu May 6 07:22:12 EDT 2021
The following Power Outage has been Confirmed:
Outage: SL-PP5
Proposed By: kujawa
Start Time: 05/07/2021 07:00
End Time: 05/07/2021 10:00
Description/Impacts:
Panel SL-PP5 will be shutdown for a breaker swap. Work will take approximately 30-45 minutes.
Awaiting on OPS for an exact start time.
Impacted Areas:
Bldg 02: South LINAC
For more details, visit the webpage listed below:
https://cc.jlab.org/cgi-bin/infrastructure/Outage/OutageView?ident=9