The following Power Outage has been Completed:
Outage:      SL-PP5
Proposed By: kujawa
Start Time:  05/07/2021 07:00
End Time:    05/07/2021 10:00
Description/Impacts:
Panel SL-PP5 will be shutdown for a breaker swap. Work will take approximately 30-45 minutes.
Awaiting on OPS for an exact start time.
Impacted Areas:
	Bldg 02: South LINAC
For more details, visit the webpage listed below:
https://cc.jlab.org/cgi-bin/infrastructure/Outage/OutageView?ident=9
    
    