The following Power Outage has been Confirmed:
Outage: B60 CUP 480 Meter Installation
Proposed By: J. Willoughby
Start Time: 03/24/2022 07:00
End Time: 03/24/2022 12:00
Description/Impacts:
Remove power from TL100 to install new meter. This will remove all 480/120 power in the building
Impacted Areas:
Bldg 60: Chiller Utility Plant
For more details, visit the webpage listed below:
https://cc.jlab.org/cgi-bin/infrastructure/Outage/OutageView?ident=44