[Utility Outage] Cancelled Power Outage - 09/28/2022 13:00

J. Willoughby jasonw at jlab.org
Tue Sep 27 11:03:16 EDT 2022


The following Power Outage has been Cancelled:

Outage:      CMSA Outage
Proposed By: J. Willoughby
Start Time:  09/28/2022 13:00
End Time:    09/28/2022 15:00

Description/Impacts:
Remove power from the CMSA to install power metering.  All buildings within the CMSA will be powered off.  The gate, compactors, cameras, and service buildings will all have no power during this outage.

Impacted Areas:
	Bldg 32A: Spill Response Storage
	Bldg 32B: Flammable Storage
	Bldg 32C: CorrosiveStorage
	Bldg 32D: Chemical Storage
	Bldg 32E: Waste Oil Storage
	Bldg 34: Mat. Handling Equip. Storage 1

For more details, visit the webpage listed below:
https://cc.jlab.org/cgi-bin/infrastructure/Outage/OutageView?ident=3