The following Power Outage has been Cancelled:

Outage:      Building 19 & 13
Proposed By: J. Willoughby
Start Time:  09/28/2022 08:00
End Time:    09/28/2022 10:00

Description/Impacts:
Remove power from Building 19 and Building 13 to install power meters.  This will remove power from all of Building 13, and impact all 208/120 power in the shop area of B19.  Lighting and receptacles will be off during this time.

Impacted Areas:
	Bldg 13: Facilities Storage Shed
	Bldg 19: Facilities Maintenance Shop