[Utility Outage] Completed Power Outage - 12/08/2025 07:00

dunlap at jlab.org dunlap at jlab.org
Mon Dec 15 13:28:59 EST 2025


The following Power Outage has been Completed:

Outage:      Hall B, B91 Beam Dump, & B92 Service Bldg.  OUTAGE/PMs
Proposed By: Howard Dunlap
Start Time:  12/08/2025 07:00
End Time:    12/12/2025 15:00

Description/Impacts:
OUTAGE PLAN FOR NEXT WEEK: 

12/8 – 94-MDP-TB – Hall B Truck Ramp (8 hours)

 

12/9 – 92-SBB1 – B92 and B91 (8 hours)

 

12/10-12/11 – 92-BCPH1 – Hall B Clean Power (16 hours)

 

12/12 – 92-SWBD-ESB – Hall B Utility Power (Meter install by subcontractor as well) (8 hours)


*The entire Hall B, B91 Beam Dump, & B92 Service Bldg. will be affected with the exception of emergency power. *

 

Impacted Areas:
	Bldg 91: Beam Dump Cooling Building A
	Bldg 92: Service Building
	Bldg 94: Experimental Hall B

For more details, visit the webpage listed below:
https://cc.jlab.org/cgi-bin/infrastructure/Outage/OutageView?ident=26