The following Power Outage has been Confirmed:
Outage: Shutdown Panels P3H5, P3L6, & P3L6A
Proposed By: Howard Dunlap
Start Time: 01/14/2026 07:00
End Time: 01/14/2026 15:00
Description/Impacts:
We will be shutting down panels P3H5, P3L6, & P3L6A to remove the existing transformer, which is currently very loud, and install a new transformer. Only systems located in Room 1137 will be affected. The system owner has been notified and has approved this work.
Impacted Areas:
Bldg 58: Test Lab