The following Power Outage has been Completed:

Outage:      Shutdown Panels P3H5, P3L6, & P3L6A
Proposed By: Howard Dunlap
Start Time:  01/14/2026 07:00
End Time:    01/14/2026 15:00

Description/Impacts:
We will be shutting down panels P3H5, P3L6, & P3L6A to remove the existing transformer, which is currently very loud, and install a new transformer. Only systems located in Room 1137 will be affected. The system owner has been notified and has approved this work.

Impacted Areas:
	Bldg 58: Test Lab

For more details, visit the webpage listed below:
https://cc.jlab.org/cgi-bin/infrastructure/Outage/OutageView?ident=1