[FFA_CEBAF_Collab] test beams
Jay Benesch
benesch at jlab.org
Fri Sep 2 12:54:01 EDT 2022
Colleagues,
Another possible justification for the LERF work.
Background: the MOLLER main detector folks have had to travel to Mainz
for electron test beams. They must schedule months in advance to get
one or two days. Similarly, SoLID calorimeter folks have run tests for
a day or two at FNAL test beams at long intervals. Test beams are in
high demand throughout the HENP community.
Could the LERF installation be configured in at least the 650 MeV
incarnation, if not both, with a test beam line? Or multiple lines with
500 MHz RF separators? These could operate as such only during main
machine SADs, and perhaps only one month a year given Operations
staffing, but would still fulfill a community need. If the incremental
cost is low enough, another point in favor of the upgrade.
For that matter, material irradiation venues are even rarer than test
beams because the exposure duration is so long in most. Perhaps the
shielded region around the positron conversion target could be used for
this en passant.
Jay
More information about the FFA_CEBAF_Collab
mailing list