[Halla_running] [New Logentry] RC Status update (Monday)

brads at jlab.org brads at jlab.org
Mon Feb 8 15:25:02 EST 2016


Logentry Text:
--
<hr/>
<strong>Exec summary</strong>
<hr/>

<ul>
  <li><strong>NOTE: As we have started taking beam it is <em>CRITICAL</em> that no one
  modifies/tests/perturbs any production system (DAQ, BCM, Raster signals,
  detector, trigger control files, prescales, etc...) without consulting
  experts and <u>always</u> making a halog entry.</strong>
  <ul>
    <li>Please leave all Counting House shift computers in a clean state for
    the next shift crew (No non-mission-critical web browsers, PDF files,
    terminal windows cluttering screens, etc.)
  </li></ul>
  </li><li>BCM calibration completed
  </li><li>DVCS/LHRS coincidence peak was observed where expected
  <ul>
    <li>See <a href="https://logbooks.jlab.org/entry/3376942">https://logbooks.jlab.org/entry/3376942</a>
  </li></ul>
  </li><li>Raster problem as been solved
  </li><li>The Hall has been in Controlled Access since the as of 8am for the following
  primary tasks:
  <ul>
    <li>Target cool down
    </li><li>Investigate raster [Done, fixed]
    </li><li>Investigate remaining problematic Harps (1C17, 1H00)
    </li><li>Move the LHRS -> 15deg, set the DVCS calorim to quasi-elastic kin.
    </li><li>Install sieve plate on RHRS
  </li></ul>
  </li><li>We will come back up at 1-Pass and execute the following:
  <ul>
    <li>Complete the target/beam alignment study
    </li><li>Do a BPM calibration/Bull's Eye scan
    </li><li>Begin the 1-pass optics studies for DVCS and GMp
  </li></ul>
  </li><li>additional details below...
</li></ul>
<hr/>
<strong>Hall Punchlist</strong>
<hr/>

<ul>
  <li>Everyone needs to read and sign the COO/ESAD/RSAD in the Counting House
  <ul>
    <li>See also <a href="https://logbooks.jlab.org/entry/3375013">https://logbooks.jlab.org/entry/3375013</a>
  </li></ul>
  </li><li>Harp scanners look generally OK, a couple of problems though
  <ul>
    <li>See <a href="https://logbooks.jlab.org/entry/3376480">https://logbooks.jlab.org/entry/3376480</a>
    </li><li>1H00 is strange, 1C17 is <em>not</em> working.  Both being looked at Monday.
  </li></ul>
  </li><li>Raster issues/questions
  <ul>
    <li>Raster hardware issues should be fixed
    <ul>
      <li>See <a href="https://logbooks.jlab.org/entry/3377029">https://logbooks.jlab.org/entry/3377029</a>
      </li><li>Possible swapping of raster signal to DAQ mapping [Barak, fixed?]
      <ul>
        <li><a href="https://logbooks.jlab.org/entry/3375810">https://logbooks.jlab.org/entry/3375810</a>
      </li></ul>
    </li></ul>
  </li></ul>
  </li><li>Position, Energy, Current locks (and FFB) status unclear [MCC, Brad]
  <ul>
    <li>MCC still working on it (reminded them yet again this morning)
  </li></ul>
  </li><li>Beam position studies
  <ul>
    <li>We have been unable to steer through the 1cm ID "Raster Target" hole
    </li><li>We have not been able to image the Carbon Hole target.
    </li><li>We will revisit this at first beam this afternoon.
  </li></ul>
  </li><li>"Suspicious activity of VDC and straw chamber in LHRS", status update?
  <ul>
    <li><a href="https://logbooks.jlab.org/entry/3376348">https://logbooks.jlab.org/entry/3376348</a>
  </li></ul>
  </li><li>Analyze BCM calibration data and get it posted
  <ul>
    <li>Update software coefficients as needed
    </li><li>See also <a href="https://logbooks.jlab.org/entry/3377095">https://logbooks.jlab.org/entry/3377095</a>
  </li></ul>
  </li><li>Arc Scanner Harp controls [new screen] does not work
  </li><li>Old (1 MHz) D1 BCM seems to drift, not clear if this is a serious problem or
  if the drift is just below the region of relevance for that (high-current)
  readback.  [Kijun, Mack, et al]
  </li><li>Need to verify that the alarm handlers all make noise (ie. audible alarm)
  <ul>
    <li>LeCroy HV controls [sound working now, HV alarms need to be tested]
    </li><li>Hall A general ALH [working]
    </li><li>Target ALH  [fix in progress?]
  </li></ul>
  </li><li>CODA EPICS logging still has a few missing/dead variables(?) [Alex, et al]
  </li><li>Arc scanner needs to be greased/oiled [Doug]
  <ul>
    <li>motion does work though, just makes a bad noise...
  </li></ul>
  </li><li>An updated Hall A BCM average current screen that uses the new BCM readouts
  has been requested, OPS/SW working on it [Brad, Kjeldsen, Alex]
  </li><li>RHRS dipole showing some puzzling readbacks
  <ul>
    <li>It's OK at 0.75 GeV, but we should not change momentum without talking to Jack
  </li></ul>
  </li><li>Significant issue with Moller target [Sasha, Roman]
  <ul>
    <li>target position/angle shifts when magnet ramped up, can not maintain alignment
    </li><li>segment of upstream beamline will be opened on Tuesday during Beam Studies
    to implement (temporary) fix
  </li></ul>
</li></ul>
<hr/>
<strong>Completed Punchlist Items (new)</strong>
<hr/>
- LHRS L1-Accept scaler double counting solved: <a href="https://logbooks.jlab.org/entry/3377026">https://logbooks.jlab.org/entry/3377026</a>
- VDC gas flow fluctuations on feedbacks are within expectations
- Raster problems fixed<br/>
- BPM strangeness investigated, best guess is MCC steering procedure not quite
  right.  This has been clarified by Yves and passed on to Crew Chiefs to be
  implemented from now on.

<ul>
  <li>HRS Magnet issues solved (mostly)! [Segal]
  <ul>
    <li>See <a href="https://logbooks.jlab.org/entry/3375822">https://logbooks.jlab.org/entry/3375822</a>
    </li><li>Left Q1 has limit of 1800A, but <em>stay below 1600A</em> for time being
    <ul>
      <li>We need to ensure shift crew have appropriate instructions on how to set
      the LHRS momentum correctly given this limitation.
    </li></ul>
    </li><li>Right Q1 <em>is</em> working: 800 A software limit
    </li><li>RHRS should stay at 0.75GeV for now
  </li></ul>
  </li><li>BCM readouts are reported to be working [Alex, Musson, Mack, Ciprian]
  <ul>
    <li>need to keep an eye on this though...
  </li></ul>
</li></ul>
<hr/>
<strong>Tentative plan for the near term</strong>
<hr/>
<u>Monday DAY</u>

<ul>
  <li>Hall A will go to Controlled Access for target cooldown
  </li><li>Move LHRS to 15 degrees
  <ul>
    <li>Sieve plates installed on RHRS only at this time
  </li></ul>
  </li><li>We will come back up at 1-pass after the target is cold
</li></ul>
<p><u>Monday SWING --> for a few good integrated shifts</u>
</p>
<ul>
  <li>1-pass beam, NO Compton chicane
  </li><li>Initial RHRS settings: P0 = 0.75 GeV/c, Angle = 48.75
  <ul>
    <li>Do NOT change the RHRS setting without contacting RC
    </li><li>Sieve plate: ON
  </li></ul>
  </li><li>Initial LHRS settings: P0 = ~2.1(?)  GeV/c, Angle = ~15 deg
  <ul>
    <li>Sieve plate: OFF to start, will install during SWING if possible, or first
    thing Tuesday DAY shift
  </li></ul>
  </li><li>Tasks will include (see <a href="https://hallaweb.jlab.org/wiki/index.php/Beamline">https://hallaweb.jlab.org/wiki/index.php/Beamline</a> )
  <ul>
    <li>Establish energy, position and current locks (and FFB) [MCC]
    </li><li>Beam centering and BPM/Raster checks
    </li><li>BPM calibration vs Harps ("Bull's Eye Scan")
    <ul>
      <li>LHRS / DVCS checkout
      </li><li>RHRS checkout: 
      <a href="https://hallaweb.jlab.org/wiki/index.php/HRS_Checkout_%28Experts%29">https://hallaweb.jlab.org/wiki/index.php/HRS_Checkout_%28Experts%29</a>
      <a href="https://hallaweb.jlab.org/wiki/index.php/HRS_Detector_Calibrations">https://hallaweb.jlab.org/wiki/index.php/HRS_Detector_Calibrations</a>
      </li><li>Run GMp optics calibrations studies (priority task)
      <ul>
        <li><a href="https://hallaweb.jlab.org/wiki/index.php/Spectrometer_Optics_First_pass_48p8d">https://hallaweb.jlab.org/wiki/index.php/Spectrometer_Optics_First_pass_48p8d</a>
      </li></ul>
    </li></ul>
    </li><li>ARC energy measurement [Doug]
    </li><li>Set LHRS DAQ to readout FADC in LHRS (low priority)
    </li><li>...
  </li></ul>
</li></ul>
<p><u>Tuesday DAY: Beam Studies</u>
</p>
<ul>
  <li>MCC has 8 hours of Beam Studies during DAY shift
  </li><li>Survey group will come in to measure the LHRS (at 15 degrees) at 9am
  <ul>
    <li>requested survey of center hole on LHRS Sieve plate, if possible
    </li><li>requested survey of target wire fiducials, if possible
  </li></ul>
  </li><li><em>IF 1-pass optics work is completed, then we will come back up at 2-pass,
  otherwise stay at 1-pass and complete optics work</em>
</li></ul>
<p><u>Wednesday DAY --> Weekend</u>
</p>
<ul>
  <li>Pass change to 2-pass (if not already done)
  <ul>
    <li>move the RHRS to largest angle (~55 degrees), so DVCS calorimeter can
    reach 20 degrees
    </li><li>go THROUGH the Compton Chicane this time
    </li><li>Yves and Compton experts (Gaskell) need to be on-shift during steer up to
    make sure the Compton is threaded well
  </li></ul>
  </li><li>Run 2-pass production quality beam
  </li><li>Complete remaining DVCS calibration tasks and/or pending beamline
  commissioning tasks
  </li><li>Ensure Position, Energy, Current locks (and FFB) is (finally!) enabled
  </li><li>Possible Moller commissioning and/or dedicated Compton Commissioning
  </li><li>Run 2-pass DVCS production setting
  </li><li>...
</li></ul>


---

This is a plain text email for clients that cannot display HTML.  The full logentry can be found online at https://logbooks.jlab.org/entry/3377100
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/halla_running/attachments/20160208/b5071e5c/attachment.html>


More information about the Halla_running mailing list