[Halla_running] [New Logentry] RC daily update
shujie at jlab.org
shujie at jlab.org
Mon Mar 12 09:00:02 EDT 2018
Logentry Text:
--
Accelerator Status:
One transformer is in place, need to do some more test, then 24 hours of free running before put load on it, expected to be ready by Wednesday. Then the other transformer will be installed as well.
Now the goal is to have full power back on SATURDAY, and next week for south linac 4k->2k and machine restoration. The current schedule is to bring beam back by 28th so that we can have 18 days before April 16th.
Hall Status:
Target is warm, HRS magnets cool. Pointing survey on both arms is undergoing.
Shift:
Canceled until March 19th day shift.
---
This is a plain text email for clients that cannot display HTML. The full logentry can be found online at https://logbooks.jlab.org/entry/3544149
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/halla_running/attachments/20180312/c888d3ba/attachment.html>
More information about the Halla_running
mailing list