[Halla_running] [New Logentry] Status

sanghwa at jlab.org sanghwa at jlab.org
Mon Feb 11 08:55:02 EST 2019


Logentry Text:
--
This morning, Hall C high current test till 9:30 followed by RF work to bring 1L20 back up. Estimated time for the RF work is ~3h. Beam won't be useful and parasitic data taking not recommended. 

We will go to controlled access now. RadCon is on the way for the survey. 
For those who want a walk through training, please contact Javier (gomez at jlab.org) or Doug (doug at jlab.org). There will be one set at 10:30.

Planed work to be done during the access:
- Check UPS (Jessie)
- Put Sieve slit back (John)
- Walk through training

If you have any work to do in the hall, please contact RC and coordinate. 


---

This is a plain text email for clients that cannot display HTML.  The full logentry can be found online at https://logbooks.jlab.org/entry/3651001
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/halla_running/attachments/20190211/1eb11fbc/attachment.html>


More information about the Halla_running mailing list