[Halla_running] [New Logentry] Status update
chandan at jlab.org
chandan at jlab.org
Fri Jul 12 09:55:06 EDT 2019
Logentry Text:
--
We don't have beam since yesterday 9:30 am. MCC has performed hysteresis cycle for some of their magnets and they were retuning the machine throughout last night.
They have claimed that the machine is reproducible and the present tune is the best they have achieved in the 12-GeV era ( please see log entry: https://logbooks.jlab.org/entry/3702781).
Based on 7:45 AM meeting, MCC is expecting to deliver beam around noon.
We will ask MCC to work on Fast Feedback after we get beam in the hall. After that we will take production data on 208Pb target with raster sync and unsync. Experts will evaluate the data and based on that we will move forward.
Yesterday, the injector group has fixed the Vwien solenoid angle.
There may be pass change in the weekend.
Spin dance is proposed on Monday (day shift, according to MCC white board).
We will have our regular RC meeting at CH conference room at 3:30 PM.
Bluejeans info:
Meeting ID: 256 205 934
Direct link: https://bluejeans.com/256205934
---
This is a plain text email for clients that cannot display HTML. The full logentry can be found online at https://logbooks.jlab.org/entry/3702872
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/halla_running/attachments/20190712/cfc809b0/attachment.html>
More information about the Halla_running
mailing list