Yesterday we finished checkout and began bringing beam back into the hall at the beginning of swing. There were accelerator-side issues preventing consistent beam into the hall throughout swing, owl, and into the day today and we are working on restoring beam. We are at functional ion chamber tests as of this email awaiting completion of RF pre-amp work done by MCC.

Let's meet at 3:30pm to discuss the current status of the hall and review the plan for the coming days.
https://sbs.jlab.org/wiki/index.php/RC_meeting_and_Run_Plan,_Thursday_November_3rd <https://sbs.jlab.org/wiki/index.php/RC_meeting_and_Run_Plan,_Thursday_November_3rd>

Best,
Sebastian Seeds