[Halla_running] [New Logentry] RC Update February 9th
jeffas at jlab.org
jeffas at jlab.org
Thu Feb 9 14:55:01 EST 2023
Logentry Text:
--
We have beam on He3!
Ops spent most of yesterday fixing the optics to send beam to hall A without tripping. Finally around midnight they started harp scans, with spot sizes to big. As they were working on harps they lost connection with harp B, which required an access to the hall, which is now fixed. Finally the beam spot size was small enough around noon today and we quickly moved on through the beam checkout and on to He3. We are now running 45 uA on He3 and the last polarization was 50%.
The upstream ion chamber was a bit (~20%) higher than previously found (https://logbooks.jlab.org/entry/4127432). MCC claims it is likely some bleadthrough from hall C and they will make sure to monitor it.
The BBCal was found to have some empty blocks (https://logbooks.jlab.org/entry/4127454) covering about 20% of the active area. BBCal experts have been notified and are looking into it.
We will have a meeting today to discuss the status and issues.
Meeting:
We will meet at 3.30pm today (upstairs in the counting house) or on zoom:
https://jlab-org.zoomgov.com/j/1619032184?pwd=aWhTVWxya1ZZQzA1K2ZPSTd2ZX
Meeting ID: 161 903 2184
Passcode: 260715
---
This is a plain text email for clients that cannot display HTML. The full logentry can be found online at https://logbooks.jlab.org/entry/4127459
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/halla_running/attachments/20230209/74f86364/attachment.html>
More information about the Halla_running
mailing list