Waited for beam all day yesterday, but we managed to do EPR measurement:
https://logbooks.jlab.org/entry/4197658
https://logbooks.jlab.org/entry/4197666
https://logbooks.jlab.org/entry/4197679

Beam came back at 6PM, so we could finally do beam checkout.
We found the optimal XSOF, YSOF positions: https://logbooks.jlab.org/entry/4198020
We also scanned the carbon hole in X and Y:
https://logbooks.jlab.org/entry/4198040
https://logbooks.jlab.org/entry/4198057

Target polarization 42.3% at the end of the beam checkout:
https://logbooks.jlab.org/entry/4198063

Resumed production early owl, first with 10uA:
https://logbooks.jlab.org/entry/4198141
 and worked our way up to 45uA
Target polarization after more than a shift of running: 40.1%
https://logbooks.jlab.org/entry/4198467

Also: 
Target rupture early Monday morning:
https://logbooks.jlab.org/entry/4195983
Target replaced and aligned late Wednesday afternoon
https://logbooks.jlab.org/entry/4197304
We lost essentially one additional day of beam compared to the two days schedule for a normal cell changeover, which is much less than formerly anticipated. Kudos to target group, radcon, hall a techs, and Gary (who coordinated everyone as RC);
 
We will have the regular RC meeting at 3:30pm in the Counting House conference room.
Alternately, people can join remotely via:

https://jlab-org.zoomgov.com/j/1616220064
Meeting ID: 161 622 0064
Passcode: 314159

---

This is a plain text email for clients that cannot display HTML.  The full logentry can be found online at https://logbooks.jlab.org/entry/4198510
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/halla_running/attachments/20231013/3ef162bc/attachment.html>


More information about the Halla_running mailing list