Logentry Text:
--
RC Report 31 October 2023

"Looks like I picked the wrong week to quit amphetamines" 

After the rupture of the target cell (pictures here https://logbooks.jlab.org/entry/4212685), we have the target in Restricted Access. Since then, the GEMs crew took out one of the BB GEMs for upkeep. RadCon vacuum the enclosure and the Target group is ready to proceed. 

Obviously, no shift reports.

At the moment of this report: 
- Techs are moving the magnets. it is expected to do the survey tomorrow.
- SBS GEM was took out for maintenance. BB GEM will be placed back when techs were available
- Target group will work on the enclosure, removing ladder, broken cell, and preparing the periscopes and mirrors. 
- Jiwan access the hall to work in the DAQ bunker. 

Tomorrow morning is expected a guided visit of the MOLLER project manager hosted by Ciprian. Zac already sent instructions of safeness for this visit, which, in principle, won't interrupt the planned work.

*-*-*-*-*-*-*-*-*-*-*-*-*-*-*-*-*-*-*-*-*-*-*-*-*-*-*-*-*-*-

We will have the regular RC meeting at 3:30pm in the Counting House conference room.
People can join remotely via:
https://jlab-org.zoomgov.com/j/1616220064
Meeting ID: 161 622 0064
Passcode: 314159

Did you know that The Eiffel Tower can be 15 cm taller during the summer due to thermal expansion? Now you know



---

This is a plain text email for clients that cannot display HTML.  The full logentry can be found online at https://logbooks.jlab.org/entry/4212974
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/halla_running/attachments/20231031/aa1660cd/attachment-0001.html>


More information about the Halla_running mailing list