OPS has successfully completed ORFP (the restoration and finalization procedure), and in addition completed some work on the 4th pass separator. Everything is on track to deliver tune beam to hall C overnight and CW tomorrow with hall A following on Tue.

Tomorrow is a maintenance day so RadCon will be very busy opening up different areas. OPS will have right of way, but we are on the schedule to get support for the target work as soon as possible. 

---