Logentry Text:
--
The plan is for hall A to be placed in controlled access tomorrow (Jun 17).
I just got off the phone with RAD CON, they explained that Hall A is 4th in the order and there will be 3 sweep teams starting at 7:45.
He could not give me a firm time estimate, but would let me know when the sweep starts. Rad Con will contact Lawrence before they go in to lock out the SBS.
I expect that we will be in controlled for most of day shift.
Currently planned work items are:
- Don Jones wants to install some shielding, he'll have some techs with him (3 Keys)
- GEM Crew would like to replace a MPC Card on GEM bunker (3 Keys)
- A few Items need to be surveyed by rad con to be removed from the hall (subject to Rad Con Availability)
- ECAL crew want to check some channels (2 Keys)
Let the Shift lead know before you go in the hall, and let me know if there is any other work that needs doing.
Thanks,
Nathan Heinrich
---
This is a plain text email for clients that cannot display HTML. The full logentry can be found online at https://logbooks.jlab.org/entry/4399121
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/halla_running/attachments/20250616/ab10c01c/attachment.htm>
More information about the Halla_running
mailing list