A quick update.
The hall is in controlled, everyone who had work to do should be getting to it. I'd like work to be planned to finish by 2pm so that we can unlock the SBS by 3pm.
Please let the shift crew know before you go down.
Last night we had network problems with both the GEM and ECAL HV supplies.
The GEMs required an access to fix, done at ~9pm last night.
It was decided that we would wait until today to fix the ECAL because there was only 12 bars affected.
ECAL fixing is now added to the list of work in the hall today.
Also, big announcement at the PD meeting this morning is that tomorrow Day shift (Wednesday the 18th) will be beam studies for Moller.
This means they will be sending test beam into the hall. So no Production data will be available for most of day shift.
Thanks,
Nathan
---
This is a plain text email for clients that cannot display HTML. The full logentry can be found online at https://logbooks.jlab.org/entry/4399731
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/halla_running/attachments/20250617/e4508625/attachment.htm>
More information about the Halla_running
mailing list