Doug Tilles tilles at jlab.org
Mon Mar 21 06:34:45 EDT 2011


Denny

Need to install the scattering chamber first thing so I can set Z before 
the alignment group get in. Then set up the rest of the upstream beam 
line for Alignment on Wed. Once the alignment group is done today we can 
pull back the target for hook up. around 1:00 today.

Doug